This excerpt taken from the AEP 10-K filed Mar 1, 2005. 1.9.2 Planned Outages.
(a) A Generator Planned Outage shall be included in Generator Planned Outage schedules established prior to the scheduled start date for the outage, in accordance with standards and procedures specified in the PJM Manuals.
(b) The Office of the Interconnection shall conduct Generator Planned Outage scheduling for Capacity Resources in accordance with the Reliability Assurance Agreement, the Reliability Assurance Agreement-West, and the PJM Manuals and in consultation with the Members owning or controlling the output of Capacity Resources. A Market Participant shall not be expected to submit offers for the sale of energy or other services, or to satisfy delivery obligations, from all or part of a generation resource undergoing an approved Generator Planned Outage. If the Office of the Interconnection determines that approval of a Generator Planned Outage would significantly affect the reliable operation of the PJM Region, the Office of the Interconnection may withhold approval or withdraw a prior approval. Approval for a Generator Planned Outage of a Capacity Resource shall be withheld or withdrawn only as necessary to ensure the adequacy of reserves or the reliability of the PJM Region in connection with anticipated implementation or avoidance of Emergency procedures. If the Office of the Interconnection withholds or withdraws approval, it shall coordinate with the Market Participant owning or controlling the resource to reschedule the
Generator Planned Outage of the Capacity Resource at the earliest practical time. The Office of the Interconnection shall if possible propose alternative schedules with the intent of minimizing the economic impact on the Market Participant of a Generator Planned Outage.
(c) The Office of the Interconnection shall conduct Transmission Planned Outage scheduling in accordance with procedures specified in, as applicable, the East Transmission Owners Agreement or West Transmission Owners Agreement and the PJM Manuals, and in accordance with the following procedures:
In addition, if the Office of the Interconnection determines that transmission maintenance schedules proposed by one or more Members would significantly affect the efficient and reliable operation of the PJM Region, the Office of the Interconnection may
establish alternative schedules, but such alternative shall minimize the economic impact on the Member or Members whose maintenance schedules the Office of the Interconnection proposes to modify.
(d) The Office of the Interconnection shall coordinate resolution of outage or other planning conflicts that may give rise to unreliable system conditions. The Members shall comply with all maintenance schedules established by the Office of the Interconnection.
|
| |||||||