These excerpts taken from the C 10-K filed Feb 22, 2008. Annual 1. PERFORM FULL FUNCTIONAL BLACKOUT TEST 2. PERFORM MAINTENANCE ON ATS SWITCHES 3. CONFIRM ELEVATOR OPERATION ON EMERGENCY POWER 4. PERFORM INSULATION RESISTANCE TESTING 5. PERFORM INFRARED SCAN OF EMERGENCY DIST GEAR UNDER LOAD. 6. PERFORM CHANGE OF LUBRICATION OIL
Sch-4-1
7. REMOVE COOLANT SAMPLE AND SEND FOR ANALYSIS Annual 1. CLEAN COILS, EVAPORATOR DRAIN PAN, BLOWER, MOTOR, AND DRAIN PIPING AS REQUIRED. 2. LUBRICATE SHAFT AND MOTOR BEARING 3. TOUCH UP PAINT AS REQUIRED 4. REPAIR INSULATION AS REQUIRED Annual 1. REMOVE CONDENSER HEADS AND PUNCH TUBES 2. REMOVE EVAPORATOR HEADS AND PUNCH TUBES 3. PERFORM EDDY CURRENT ON CONDENSER 4. PERFORM EDDY CURRENT ON EVAPORATOR 5. WIRE WHEEL AND APPLY ANTI-CORROSIVE TO ALL SURFACES 6. REMOVE REFRIGERANT SAMPLE AND SEND OUT FOR ANALYSIS 7. PERFORM INSULATION RESISTANCE TESTING | EXCERPTS ON THIS PAGE:
RELATED TOPICS for C: |
| |||||||