This excerpt taken from the C 10-K filed Feb 22, 2008. System-Wide Maintenance 1. VISUALLY INSPECT ALL ALARM EQUIPMENT FOR OBSTRUCTIONS OR PHYSICAL DAMAGE, CLEAN DIRT AND DUST FROM INTERIOR AND EXTERIOR OF PANEL/PULL BOXES, TIGHTEN LOOSE CONNECTIONS. 2. CONDUCT OPERATIONAL TEST OF INITIATING AND SIGNAL TRANSMITTING DEVICES IN POPULATED BUILDINGS BY BUILDING ZONE/AREA, FOR THOSE CIRCUITS WHICH DO NOT OPERATE PROPERLY, CHECK DETECTORS, CONTROL UNITS, AND ANNUNCIATORS FOR DUST ON DEFECTIVE COMPONENTS, 3. CHECK BATTERY VOLTAGES WHERE INSTALLED, REPLACE AS REQUIRED. 4. RESTORE SYSTEM TO PROPER OPERATING CONDITION AND NOTIFY PERSONNEL UPON COMPLETION OF TESTS. 5. FILL OUT MAINTENANCE CHECKLIST AND REPORT DEFICIENCIES. |
| |||||||