This excerpt taken from the GPS 10-K filed Mar 28, 2006. Server Consolidation and Migration As part of the agreement, IBM will consolidate the initial quantity of server images per the baselines in Exhibit C-13 (Image Consolidation Baseline) and the images in Exhibits C-2, C-3, and C-10 of the Agreement. * The IBM plan includes three phases for the planned server consolidation and migration:
During phase 1 the Gap IT enterprise will be documented and will then undergo a *. This collaborative effort between Gap and IBM will *. During phase 2, in a collaborative effort, * and a complete transformation plan will be created to meet the computing requirements of the business units. Finally, during phase 3, IBMs consolidation team will *. |
| |||||||