This excerpt taken from the PCG 10-K filed Feb 18, 2005. Purpose and Objectives These Path 15 Operating Instructions provide direction to the ISO regarding the management of congestion on Path 15 during the ISO's Day Ahead, Hour Ahead and Real Time markets. The objective of these instructions is to assure, on an ongoing basis, the efficient use each day of available Path 15 transfer capability while maintaining the transmission rights and priorities on Path 15 that were in existence as of the ISO Operations Date. These instructions also clarify individual and joint responsibilities between the ISO as the Control Area Operator and PG&E as the Path 15 Existing Transmission Contract (ETC) Facilitator.1 These instructions are to be adhered to except when the ISO determines that system reliability requires that other steps be taken. The ISO is solely responsible for continued system reliability and must unilaterally take all steps necessary to preserve the system in times of emergency.
|
| |||||||