PCG » Topics » SPECIFIC REQUIREMENTS

This excerpt taken from the PCG 10-K filed Feb 18, 2005.

SPECIFIC REQUIREMENTS

Note 1:   This section identifies the operational requirements for the SONGS offsite power supply. These requirements are part of the SONGS design basis and licensing basis. Failure to meet these requirements may render the offsite power supply Inoperable, thus requiring the operating SONGS unit(s) to shutdown. Failure to meet these requirements must be immediately communicated to SCE and the SONGS Control Room for operability determination. Changes in the operation of the transmission network that conflict with these requirements require prior approval by SCE.

Note 2:

 

Specific requirements, procedures, operating bulletins, division orders, and analysis that support or provide the basis for the specific operational requirements may be revised periodically subject to prior approval of the affected parties.
1.
Nine transmission lines into the SONGS switchyard are normally in service. Any increase or decrease in the number of lines into the SONGS switchyard requires prior approval of SCE. (Reference 7)

    No line may be removed from service for greater than 30 days without prior notification to SCE. At least two independent transmission lines (one from SCE and one from SDG&E) between the transmission network (grid) and SONGS switchyard shall be in service at all times. (References 1, 2, 3, 4, 7, 8)

2.
With both San Onofre units off-line, the SONGS offsite power source shall be capable of providing 158 MW and 96 MVAR to San Onofre for normal operation and for shutting down the units during plant Design Basis Accident (DBA) conditions. (References 9, 10)

3.
The minimum grid voltage at the SONGS switchyard shall be maintained at or above 218 kV. In the event of a system disturbance that can cause the voltage to dip below 218 kV, including the trip of a SONGS unit, the grid voltage shall recover to 218 kV or above within 2.5 seconds. (References 9, 10, 12, 13, 18)

4.
The following initiating events shall not result in the loss of grid stability or availability:
a.
The loss of a San Onofre Unit (with the other unit already offline), or

b.
The loss of any generating unit on the SCE and SDG&E grids, or

c.
The loss of any major transmission circuit or intertie on the SCE and SDG&E grids, or

d.
The loss of any large load or block of load (e.g., due to a bus section outage) on the SCE and SDG&E grids.

    (References 2, 3, 4, 8)

5.
The maximum grid voltage at the SONGS switchyard shall be maintained at or below 238 kV. (References 10, 11, 18)

6.
The normal operating voltage of the SONGS switchyard shall be maintained at 230 kV. The SONGS switchyard voltage shall not exceed 232 kV unless required to preserve transmission network integrity. (References 10, 11, 18)

7.
The limiting conditions for SONGS offsite power source operability are defined as follows:
1.
One SONGS unit is off- line, and
2.
One of the critical line (s) outages occurs (see list of the lines below), and
3.
VAR flows north and south of SONGS are above the threshold levels for the existing combined SCE and SDG&E import level as defined by the referenced nomograms in the GCC Operating Procedure: SONGS Voltage (Current revision).

79


    Based on these nomograms and SONGS offline unit's status, if the Grid Control Center or ISO determines that the operating point is outside the applicable derated nomogram line, they shall notify SONGS immediately that a particular transmission line is out of service, and the critical system conditions are sufficient to cause SONGS off site power source to be considered INOPERABLE; i.e., unable to support SONGS voltage at 218 kV if the remaining unit trips. SONGS Control Room will declare the offsite source inoperable (in anticipation of losing the second SONGS unit) and will declare the time period within which the on-line unit will have to initiate shutdown if conditions are not corrected. The time period will be within 1 to 24 hours, based on the SONGS plant and equipment conditions.

      List of critical transmission lines/grid conditions:

      Critical Line(s) Out In SCE Territory

      Palo Verde -Devers 500 kV Line
      Ellis- Johanna & Ellis-Santiago 230 kV Lines
      Lugo-Serrano & Mira Loma-Serrano 500 kV Lines
      Lugo- Mira Loma 2&3 500 kV Lines
      Two Midway - Vincent 500 kV Lines
      SONGS- Serrano & SONGS - Chino 230 kV Lines

      Critical Line(s) Out in SDG&E Territory

      Hassayampa-N. Gila 500 kV Line
      N. Gila- Imperial Valley 500 kV Line
      Imperial Valley- Miguel 500 kV Line
      Imperial Valley- Miguel 500 kV Line & Imperial Valley- LaRosita 230 kV Line
      SONGS-San Luis Rey 230 kV Tap & SONGS - Mission 230 kV Line

      Critical Grid Conditions:
      SCE/SDG&E Tie Separation at SONGS:

      SCE/SDG&E Tie Open, Unit 3 On-Line (Unit 2 Off-Line)
      SCE/SDG&E Tie Open, Unit 2 On-Line (Unit 3 Off-Line)

    Systems studies shall be performed and updated based on changing grid conditions (load growth, etc.) to identify critical conditions, such as the above cases, that could render the offsite power supply Inoperable. The offsite power system is considered Inoperable if it is degraded to the point that it does not have the capability to provide electrical support to safe shutdown loads and to mitigate the effects of an accident at SONGS. This level of degradation can be caused by an unstable offsite power system, or any condition which renders the offsite power supply unavailable for safe shutdown and emergency purposes. The following actions are required:

    a.
    Procedures and programs shall be in effect to ensure that the SONGS Control Room is immediately notified of such conditions.

    b.
    Grid conditions that are more severe with respect to SONGS switchyard voltage, or are otherwise unanalyzed, render the offsite power supply Inoperable. The SONGS Control Room shall be immediately notified of such conditions.

    c.
    Auditable records of current system studies shall be made available to SCE as needed to demonstrate compliance with regulatory requirements. Study results, including revisions and updates, shall be formally transmitted to SCE.

    d.
    Study results and conclusions shall be assessed at least annually and updated, if needed, based on changing grid conditions. Results of the annual assessments shall be formally transmitted to SCE.

80


(References 1, 2, 19, 21)

    System studies shall consider the interconnections between SCE, SDG&E, and other utilities in the Western Electricity Coordinating Council (WECC). (Reference 7)

8.
In the event of loss of the SONGS offsite power supply:

Note:
SONGS 2 and 3 are required by NRC regulations to be able to safely cope with a loss of all AC power (Station Blackout) for a maximum of four hours. The four hour coping duration is based on the expectation that at least one source of AC power (offsite transmission line or onsite diesel generator) will be restored to the blacked-out unit within the four hours to ensure the proper functioning of systems required for plant safety.

a.
Highest possible priority shall be given to restoring power to the SONGS switchyard. Procedures and training should consider several potential methods of transmitting power from black-start capable units to the SONGS switchyard. This includes such items as nearby gas turbine generators, portable generators, hydro generators, and black-start fossil power plants. (References 15, 26, 28)

b.
Should incoming lines to the SONGS switchyard be damaged, highest priority shall be assigned to repair and restoration of at least one line into the SONGS switchyard.

c.
Repair crews engaging in power restoration activities for SONGS shall be given the highest priority for manpower, equipment, and materials.

d.
Formal programs and procedures shall be in place to effect items a, b, and c above.

(References 14, 15, 16, 17, 26, 27)

9.
Grid frequency shall be maintained at 60 Hertz (nominal). A trip of one SONGS unit shall not cause the grid frequency to dip below 59.7 Hertz. SCE and SDG&E comply with the WECC Coordinated Off-Nominal Frequency Load Shedding and Restoration Plan.

Note:
System separation between SCE and SDG&E at the SONGS bus tie on low grid frequency mentioned in the previous version of the TCA is being removed from SONGS by mid-2002. Increased load shedding schemes by SDG&E have been implemented which preclude the need for system separation at SONGS bus ties on low frequency.

(References 7, 20)

10.
SCE and SDG&E Bulk Power Transmission System Reliability Criteria as described in the SONGS 2&3 Updated Final Safety Analysis Report shall be maintained. It is recognized that the SCE and SDG&E Bulk Power Transmission System Reliability Criteria as described in the SONGS 2&3 Updated Final Safety Analysis Report may be revised from time to time. In the event the reliability criteria are revised, a system assessment and/or study (as described under specification 7) shall be performed to determine if the revised reliability criteria adversely impact grid reliability and availability as defined in this specification. Results of the assessment and/or study together with a copy of the revised reliability criteria shall be provided to SCE. Changes in grid operation based on the revised criteria and associated studies shall not be implemented without prior approval of SCE. (Reference 7)

11.
Patrol and inspection of SCE and SDG&E transmission lines shall be performed in accordance with the current ISO approved Overhead Electric Transmission Line Maintenance Practice or as required by the NRC plant-operating license, whichever requirement is more stringent. These patrols and inspections are to ensure that the physical and electrical integrity of transmission system components are maintained. (Reference 7)

81


12.
Line insulators on lines which carry power from the plant to the grid shall be washed as required by the NRC plant-operating license or on an appropriate wash cycle in accordance with the current ISO approved Overhead Electric Transmission Line Maintenance Practice, whichever requirement is more stringent. The purpose and frequency of which is proven to prevent line outages that may result from flashovers due to accumulated contamination. (Reference 7)

13.
Maintenance, testing and calibration of SCE and SDG&E station equipment and protective relays shall be performed in accordance with the current ISO approved Electrical Station Maintenance Practice or as required by the NRC plant operating license, whichever requirement is more stringent. (Reference 7)

14.
Preventive maintenance and testing of SONGS switchyard batteries shall be performed per IEEE 450-1972. Preventive maintenance and testing of SONGS switchyard battery chargers and DC system components shall be performed routinely. (Reference 7, 23)

15.
Updates to applicable portions of Section 8.0, Electric Power of the SONGS 2 & 3 Updated Final Safety Analysis Report (UFSAR) shall be provided annually. These updates will be used by SCE to prepare a UFSAR change submittal to the NRC. SONGS is required by 10CFR50.71(e) to submit to the NRC periodic updates to the UFSAR.

82


Wikinvest © 2006, 2007, 2008, 2009, 2010, 2011, 2012. Use of this site is subject to express Terms of Service, Privacy Policy, and Disclaimer. By continuing past this page, you agree to abide by these terms. Any information provided by Wikinvest, including but not limited to company data, competitors, business analysis, market share, sales revenues and other operating metrics, earnings call analysis, conference call transcripts, industry information, or price targets should not be construed as research, trading tips or recommendations, or investment advice and is provided with no warrants as to its accuracy. Stock market data, including US and International equity symbols, stock quotes, share prices, earnings ratios, and other fundamental data is provided by data partners. Stock market quotes delayed at least 15 minutes for NASDAQ, 20 mins for NYSE and AMEX. Market data by Xignite. See data providers for more details. Company names, products, services and branding cited herein may be trademarks or registered trademarks of their respective owners. The use of trademarks or service marks of another is not a representation that the other is affiliated with, sponsors, is sponsored by, endorses, or is endorsed by Wikinvest.
Powered by MediaWiki