|
|
![]() | ![]() | ![]() | ![]() |
| |||||||||
This excerpt taken from the PCG 8-K filed Oct 28, 2005. Spent Nuclear Fuel Storage Proceedings
Under the Nuclear Waste Policy Act of 1982, the Department of Energy, or the DOE, is responsible for the permanent storage and disposal of spent nuclear fuel. The Utility has signed a contract with the DOE to provide for the disposal of spent nuclear fuel and high-level radioactive waste from the Utilitys nuclear power facilities. Under the Utilitys contract with the DOE, if the DOE completes a storage facility by 2010, the earliest that Diablo Canyons spent fuel would be accepted for storage or disposal would be 2018. At the projected level of operation for Diablo Canyon, the Utilitys current facilities are able to store on-site all spent fuel produced through approximately 2007. The NRC granted authorization in March 2004 to build an on-site dry cask storage facility to store spent fuel through approximately 2021 for Unit 1 and to 2024 for Unit 2. However, several intervenors in that proceeding filed an appeal of the NRCs decision with the U.S. Court of Appeals for the Ninth Circuit, or Ninth Circuit. Oral arguments on that appeal are expected in the first quarter of 2005 with a decision anticipated in the second half of 2005. Construction of the on-site dry cask storage facility is expected to start in the second quarter of 2005 after grading permits are obtained from the County of San Luis Obispo. To provide another storage alternative in the event construction of the dry cask storage facility is delayed, the Utility has also requested that the NRC approve another storage option to install a temporary storage rack in each units existing spent fuel storage pool that would increase the on-site storage capability to permit the Utility to operate Unit 1 until 2010 and Unit 2 until 2011. If the Utility is unsuccessful in permitting and constructing the on-site dry cask storage facility, and is otherwise unable to increase its on-site storage capacity, it is possible that the operation of Diablo Canyon may have to be curtailed or halted as early as 2007 and until such time as additional spent fuel can be safely stored.
This excerpt taken from the PCG 10-K filed Feb 18, 2005. Spent Nuclear Fuel Storage Proceedings Under the Nuclear Waste Policy Act of 1982, the Department of Energy, or the DOE, is responsible for the permanent storage and disposal of spent nuclear fuel. The Utility has signed a contract with the DOE to provide for the disposal of spent nuclear fuel and high-level radioactive waste from the Utility's nuclear power facilities. Under the Utility's contract with the DOE, if the DOE completes a storage facility by 2010, the earliest that Diablo Canyon's spent fuel would be accepted for storage or disposal would be 2018. At the projected level of operation for Diablo Canyon, the Utility's current facilities are able to store on-site all spent fuel produced through approximately 2007. The NRC granted authorization in March 2004 to build an on-site dry cask storage facility to store spent fuel through approximately 2021 for Unit 1 and to 2024 for Unit 2. However, several intervenors in that proceeding filed an appeal of the NRC's decision with the U.S. Court of Appeals for the Ninth Circuit, or Ninth Circuit. Oral arguments on that appeal are expected in the first quarter of 2005 with a decision anticipated in the second half of 2005. Construction of the on-site dry cask storage facility is expected to start in the second quarter of 2005 after grading permits are obtained from the County of San Luis Obispo. To provide another storage alternative in the event construction of the dry cask storage facility is delayed, the Utility has also requested that the NRC approve another storage option to install a temporary storage rack in each unit's existing spent fuel storage pool that would increase the on-site storage capability to permit the Utility to operate Unit 1 until 2010 and Unit 2 until 2011. If the Utility is unsuccessful in permitting and constructing the on-site dry cask storage facility, and is otherwise unable to increase its on-site storage capacity, it is possible that the operation of Diablo 115 Canyon may have to be curtailed or halted as early as 2007 and until such time as additional spent fuel can be safely stored. | EXCERPTS ON THIS PAGE:
RELATED TOPICS for PCG: |
| |||||||