PCG » Topics » Spent Nuclear Fuel Storage Proceedings

This excerpt taken from the PCG 8-K filed Oct 28, 2005.

Spent Nuclear Fuel Storage Proceedings

 

Under the Nuclear Waste Policy Act of 1982, the Department of Energy, or the DOE, is responsible for the permanent storage and disposal of spent nuclear fuel. The Utility has signed a contract with the DOE to provide for the disposal of spent nuclear fuel and high-level radioactive waste from the Utility’s nuclear power facilities. Under the Utility’s contract with the DOE, if the DOE completes a storage facility by 2010, the earliest that Diablo Canyon’s spent fuel would be accepted for storage or disposal would be 2018. At the projected level of operation for Diablo Canyon, the Utility’s current facilities are able to store on-site all spent fuel produced through approximately 2007. The NRC granted authorization in March 2004 to build an on-site dry cask storage facility to store spent fuel through approximately 2021 for Unit 1 and to 2024 for Unit 2. However, several intervenors in that proceeding filed an appeal of the NRC’s decision with the U.S. Court of Appeals for the Ninth Circuit, or Ninth Circuit. Oral arguments on that appeal are expected in the first quarter of 2005 with a decision anticipated in the second half of 2005. Construction of the on-site dry cask storage facility is expected to start in the second quarter of 2005 after grading permits are obtained from the County of San Luis Obispo. To provide another storage alternative in the event construction of the dry cask storage facility is delayed, the Utility has also requested that the NRC approve another storage option to install a temporary storage rack in each unit’s existing spent fuel storage pool that would increase the on-site storage capability to permit the Utility to operate Unit 1 until 2010 and Unit 2 until 2011. If the Utility is unsuccessful in permitting and constructing the on-site dry cask storage facility, and is otherwise unable to increase its on-site storage capacity, it is possible that the operation of Diablo Canyon may have to be curtailed or halted as early as 2007 and until such time as additional spent fuel can be safely stored.

 

This excerpt taken from the PCG 10-K filed Feb 18, 2005.

Spent Nuclear Fuel Storage Proceedings

        Under the Nuclear Waste Policy Act of 1982, the Department of Energy, or the DOE, is responsible for the permanent storage and disposal of spent nuclear fuel. The Utility has signed a contract with the DOE to provide for the disposal of spent nuclear fuel and high-level radioactive waste from the Utility's nuclear power facilities. Under the Utility's contract with the DOE, if the DOE completes a storage facility by 2010, the earliest that Diablo Canyon's spent fuel would be accepted for storage or disposal would be 2018. At the projected level of operation for Diablo Canyon, the Utility's current facilities are able to store on-site all spent fuel produced through approximately 2007. The NRC granted authorization in March 2004 to build an on-site dry cask storage facility to store spent fuel through approximately 2021 for Unit 1 and to 2024 for Unit 2. However, several intervenors in that proceeding filed an appeal of the NRC's decision with the U.S. Court of Appeals for the Ninth Circuit, or Ninth Circuit. Oral arguments on that appeal are expected in the first quarter of 2005 with a decision anticipated in the second half of 2005. Construction of the on-site dry cask storage facility is expected to start in the second quarter of 2005 after grading permits are obtained from the County of San Luis Obispo. To provide another storage alternative in the event construction of the dry cask storage facility is delayed, the Utility has also requested that the NRC approve another storage option to install a temporary storage rack in each unit's existing spent fuel storage pool that would increase the on-site storage capability to permit the Utility to operate Unit 1 until 2010 and Unit 2 until 2011. If the Utility is unsuccessful in permitting and constructing the on-site dry cask storage facility, and is otherwise unable to increase its on-site storage capacity, it is possible that the operation of Diablo

115



Canyon may have to be curtailed or halted as early as 2007 and until such time as additional spent fuel can be safely stored.

EXCERPTS ON THIS PAGE:

8-K
Oct 28, 2005
10-K
Feb 18, 2005
Wikinvest © 2006, 2007, 2008, 2009, 2010, 2011, 2012. Use of this site is subject to express Terms of Service, Privacy Policy, and Disclaimer. By continuing past this page, you agree to abide by these terms. Any information provided by Wikinvest, including but not limited to company data, competitors, business analysis, market share, sales revenues and other operating metrics, earnings call analysis, conference call transcripts, industry information, or price targets should not be construed as research, trading tips or recommendations, or investment advice and is provided with no warrants as to its accuracy. Stock market data, including US and International equity symbols, stock quotes, share prices, earnings ratios, and other fundamental data is provided by data partners. Stock market quotes delayed at least 15 minutes for NASDAQ, 20 mins for NYSE and AMEX. Market data by Xignite. See data providers for more details. Company names, products, services and branding cited herein may be trademarks or registered trademarks of their respective owners. The use of trademarks or service marks of another is not a representation that the other is affiliated with, sponsors, is sponsored by, endorses, or is endorsed by Wikinvest.
Powered by MediaWiki