|
|
![]() | ![]() | ![]() | ![]() |
This excerpt taken from the PALM 10-Q filed Apr 5, 2005. TERMINATION OR SUSPENSION OF THE CONTRACT
14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of 30 days through no act or fault of the Contractor or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Contractor, for any of the following reasons:
14.1.2 If one of the above reasons exists, the Contractor may, upon seven additional days written notice to the Owner and Architect, terminate the Contract and recover from the Owner payment for Work executed and for proven loss with respect to materials, equipment, tools, and construction equipment and machinery, including reasonable overhead, profit and damages.
14.1.3 If the Work is stopped for a period of 60 days through no act or fault of the Contractor or a Subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Contractor because the Owner has persistently failed to fulfill the Owners obligations under the Contract Documents with respect to matters important to the progress of the Work, the Contractor may, upon seven additional days written notice to the Owner and the Architect, terminate the Contract and recover from the Owner as provided in Subparagraph 14.1.2
14.2.1 The Owner may terminate the Contract if the Contractor:
14.2.2 When any of the above reasons exist, the Owner, upon certification by the Architect that sufficient cause exists to justify
such action, may without prejudice to any other rights or remedies of the Owner and after giving the Contractor and the Contractors surety, if any, seven days written notice, terminate employment of the Contractor and may, subject to any prior rights of the surety:
14.2.3 When the Owner terminates the Contract for one of the reasons stated in Subparagraph 14.2.1, the Contractor shall not be entitled to receive further payment until the Work is finished.
14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for the Architects services and expenses made necessary thereby, such excess shall be paid to the Contractor. If such costs exceed the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case may be, shall be certified by the Architect, upon application, and this obligation for payment shall survive termination of the Contract.
14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
14.3.2 An adjustment shall be made for increases in the cost of performance of the Contract, including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent:
14.3.3 Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.
AIA Document A111
|
| |||||||