This excerpt taken from the PBR 6-K filed Nov 19, 2009.

a) In the United States - P-19 and P-31

On July 25, 2002, Braspetro Oil Service Company (Brasoil) and Petrobras won related lawsuits filed with the US lower courts by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company since 1997. A court decision by the Federal Court of the Southern District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt related to the performance bond, totaling approximately US$ 370 million. However, an appeal filed by the insurance companies removed the obligation by the insurance companies with respect to payment of the fine, legal fees and costs, thus reducing the amount of the indemnity to US$ 245 million.

On July 21, 2006, the US court handed down an executive decision, conditioning the payment of the amounts owed to Brasoil to the permanent closing of legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

This excerpt taken from the PBR 6-K filed Aug 18, 2009.

a) In the United States - P-19 and P-31

On July 25, 2002, Braspetro Oil Service Company (Brasoil) and Petrobras won related lawsuits filed with the US lower courts by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company since 1997. A court decision by the Federal Court of the Southern District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt related to the performance bond, totaling, approximately, US$ 370 million. An appeal filed by the insurance companies removed the obligation by the insurance companies with respect to payment of the fine, legal fees and costs, thus reducing the amount of the indemnity to US$ 245 million.

On July 21, 2006, the US court handed down an executive decision, conditioning the payment of the amounts owed to Brasoil to the permanent closing of legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

This excerpt taken from the PBR 6-K filed Jun 8, 2009.

a) In the United States - P-19 and P-31

On July 25, 2002, Braspetro Oil Service Company (Brasoil) and Petrobras won related lawsuits filed with the US Lower Courts by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company since 1997. A court decision by the Federal Court of the Southern District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt related to the performance bond, totaling approximately US$ 370 million. However, an appeal filed by the insurance companies removed the obligation by the insurance companies with respect to payment of the fine, legal fees and costs, thus reducing the amount of the indemnity to US$ 245 million.

On July 21, 2006, the US Court handed down an executive decision, conditioning the payment of the amounts owed to Brasoil to the permanent closing of legal proceedings involving identical claims in progress before the Brazilian Courts, which the parties proceeded to do.

This excerpt taken from the PBR 6-K filed Mar 31, 2009.

a) In the United States - P-19 and P-31

On July 25, 2002, Braspetro Oil Service Company (Brasoil) and Petrobras won related lawsuits filed since 1997 with the US lower courts by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company. A court decision by the Federal Court of the Southern District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt related to the performance bond, totalling approximately US$ 370 million. However, an appeal filed by the insurance companies removed the obligation by the insurance companies with respect to payment of the fine, legal fees and costs, thus reducing the amount of the indemnity to US$ 245 million.

On July 21, 2006, the US court handed down an executive decision, conditioning the payment of the amounts owed to Brasoil to the permanent closing of legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

78


Table of Contents


This excerpt taken from the PBR 6-K filed Aug 13, 2008.

a) In the United States - P-19 and P-31

After a decision from the Second Circuit Court of Appeals of New York on May 20, 2004, which upheld the right of Brasoil to receive the performance bonds am ounting to approximately US$ 245.000 thousand, owed by the insurers United States Fidelity & Guaranty Company and American Home Assurance Company, Brasoil and the insurance companies began talks towards the effective settlement of the amount.

On June 21, 2006, the US courts made payment of the amount owed to Brasoil subject to the permanent discontinuance of the legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

This excerpt taken from the PBR 6-K filed Nov 21, 2007.

a) In the United States – P-19 and P-31

On July 25, 2002, Braspetro Oil Service Co. (Brasoil) and Petrobras won related lawsuits filed with an American lower court by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company, which had, since 1997, attempted to obtain a legal judgment in the United States to exempt them from the obligation to indemnify Brasoil for the construction (“performance bond”) of platforms P-19 and P-31, and from Petrobras, the refund of any amounts that they might be ordered to pay in the “performance bond” proceeding.

A court decision by the first level of the Federal Court of the District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt, relating to the performance bond, totaling approximately US$ 370 million.

The insurance companies have filed appeals against the decision with the United States Court of Appeals for the Second Circuit. A decision was handed down on May 20, 2004, when the Court partly maintained the verdict, confirming the insurance companies’ liability to pay the performance bonds and exempting the insurance companies from the obligation to pay liquidated damages, attorney’s fees and expenses, reducing the indemnity to US$ 245 million.

The insurance companies appealed against this decision to the full court, which rejected the appeal, thus confirming the unfavorable verdict as mentioned. In April 2005, the parties (Insurance companies and Brasoil) began discussions seeking to settle the credit of Brasoil, resulting in the execution of a Memorandum of Understanding, the effects of which, however, led to further queries and issues to be settled in court. On July 21, 2006, the U.S. Court delivered an executive decision specifying the points of divergence, and the interest due. However, it made payment of the amounts owed to Brasoil subject to the permanent discontinuance of the legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

This excerpt taken from the PBR 6-K filed Aug 21, 2007.

a) In the United States – P-19 and P-31

On July 25, 2002, Brasoil and Petrobras won a lawsuit filed with an American Court by the insurance companies United States Fidelity & Guaranty Company and American Home Assurance Company, which had attempted to obtain since 1997, a legal judgment in the United States to exempt them from the obligation to indemnify Brasoil for the construction (“performance bond”) of platforms P-19 and P-31, and from Petrobras, the refund of any amounts that they might be ordered to pay in the “performance bond” proceeding.

A court decision by the first level of the Federal Court of the District of New York recognized the right of Brasoil and Petrobras to receive indemnity for losses and damages in the amount of US$ 237 million, plus interest and reimbursement of legal expenses on the date of effective receipt, relating to the performance bond, in a total of approximately US$ 370 million.

The insurance companies have filed appeals against the decision with the United States Court of Appeals for the Second Circuit. A decision was handed down on May 20, 2004, when the Court partly maintained the verdict, confirming the insurance companies’ liability to pay the performance bonds and exempting the insurance companies from the obligation to pay liquidated damages, attorney’s fees and expenses, reducing the indemnity to US$ 245 million.

The insurance companies appealed against this decision to the full court, which rejected the appeal, thus confirming the unfavorable verdict as mentioned. In April 2005, the parties (Insurance companies and Brasoil) began discussions seeking to settle the credit of Brasoil, resulting in the execution of a Memorandum of Understanding, the effects of which, however, led to further queries and issues to be settled in court. On July 21, 2006, the U.S. Court delivered an executive decision specifying the points of divergence, and the interest due. However, it made payment of the amounts owed to Brasoil subject to the permanent discontinuance of the legal proceedings involving identical claims in progress before the Brazilian courts, which the parties proceeded to do.

Wikinvest © 2006, 2007, 2008, 2009, 2010, 2011, 2012. Use of this site is subject to express Terms of Service, Privacy Policy, and Disclaimer. By continuing past this page, you agree to abide by these terms. Any information provided by Wikinvest, including but not limited to company data, competitors, business analysis, market share, sales revenues and other operating metrics, earnings call analysis, conference call transcripts, industry information, or price targets should not be construed as research, trading tips or recommendations, or investment advice and is provided with no warrants as to its accuracy. Stock market data, including US and International equity symbols, stock quotes, share prices, earnings ratios, and other fundamental data is provided by data partners. Stock market quotes delayed at least 15 minutes for NASDAQ, 20 mins for NYSE and AMEX. Market data by Xignite. See data providers for more details. Company names, products, services and branding cited herein may be trademarks or registered trademarks of their respective owners. The use of trademarks or service marks of another is not a representation that the other is affiliated with, sponsors, is sponsored by, endorses, or is endorsed by Wikinvest.